Train manufacturer intentionally bricks trains serviced by independent service providers (social.hackerspace.pl)
Polish article...
![](https://kbin.cafe/media/cache/resolve/entry_thumb/b3/b7/b3b720d51b143458a3b13ce2e8cd7aefaa34deaca9a7bd66fe37245a38156579.png)
Polish article...
A polish hacker found out why trains did stop working. The manufacterer implemented a hidden electronic switch, which automatically activated after trains were serviced by a different company.
Polish train manufacturer that lost servicing tender programmed train controller to brick itself after train stays for some time in 6 ISP facilities or in 1 their faculity(for testing?) until undocumented button combination is pressed. Some controller versions brick itself after train is idle for 10 days. After news about this...
A Mastodon thread by @q3k, who, together with @redford and @mrtick have reverse engineered the PLC code of NEWAG Impuls EMUs